Construction Update January 13, 2023

posted in: Construction Updates | 0

In this issue:

  • Upcoming Traffic Control Measures
  • Construction Underway and Upcoming
  • Reminders: Forestview Creek Path and Piner High School bus stop

Upcoming Traffic Control Measures

Crews are tentatively scheduled to begin installing “roller-compacted concrete” (RCC) on Fulton Road in late February. During that period of work, additional traffic control measures will be put into place, with potentially significant temporary traffic delays anticipated. The schedule for this work is dependent on weather – more information will be provided in the coming weeks.

Construction Underway and Upcoming

The current storm systems are preventing most work from taking place at this time, but construction will resume as soon as weather permits.

When traveling in and near the construction areas, use additional caution and be aware of work crews, flaggers, traffic control, rough roadways, special signage, and heavy equipment. Please be prepared for temporary traffic control measures throughout the work area. Road construction is currently paused due to rain. However, if there are breaks in the weather work will include the following:

  • Installation of new driveways at several locations along the construction site.
  • Installation of new light posts and traffic signals.
  • Preparation of the subgrade, and forming and pouring new curbs and gutters at various locations.
  • Connecting water lines to new fire hydrants.
  • As part of their regularly scheduled maintenance program, PG&E will soon begin replacing a gas line on the west side of Fulton Road between Jenes Lane and Appletree Drive. This work is not part of the Fulton Road Widening project. PG&E scheduled the work to overlap with the widening project in order to minimize further disruptions to the public.

All schedules are subject to change due to weather and unforeseen circumstances.

Reminders:

  • As of early August, the Forestview Creek path is closed 24/7 from Fulton Road to Country Manor Drive, for the construction of a retaining wall and other concrete work near the creek.

For the protection of the creek and habitat, State environmental regulations establish the seasonal periods during which concrete work can take place in or near a creek (including the potential for rain). Crews have been working to complete those elements before the end of the allowed period, however, it is now very likely that work at the creek will be suspended until that “window” opens again in late spring of 2023.

Therefore, the Forestview Creek path is likely to remain closed to public use until late spring/early summer of 2023. An update will be provided once the anticipated schedule is finalized. We apologize for any disruption or inconvenience that this extension of the path closure may cause. As an alternative, path users may want to consider using the Peterson Creek path between Guerneville Road and Fulton Road.

  • Piner High School bus stop – The northbound temporary bus stop has been relocated back to a location near the original bus stop location, just south of the main Piner High School entrance. Work is still underway on the new bus stop at this location with an estimated reopening this winter. For general bus service information please visit Santa Rosa CityBus.

 

Installation of new traffic signal interconnect conduits
Installation of new traffic signal interconnect conduits

 

The new storm drain piping installation at Peterson Creek in operation during the recent storms
The new storm drain piping installation at Peterson Creek in operation during the recent storms

Project overview and schedule

This project will widen, reconstruct, and rehabilitate one mile of Fulton Road between Guerneville Road and Piner Road, transforming it into an updated, four-lane regional/arterial street, as well as provide many other improvements. The project is expected to continue for approximately 18 – 24 months (all schedules are subject to change depending on weather, unanticipated circumstances, and seasonal access restrictions to creek areas).

Work hours: 7 am to 7 pm Monday through Friday. With City approval, periodic work on nights (8:30 pm to 5:00 am) or weekends may take place.

Additional project overview and overall schedule information is online at www.FultonRoadProject.com.