Construction Update October 28, 2022

posted in: Construction Updates | 0

In this issue:

  • Ongoing traffic control – Piner Road/Fulton Road
  • Construction underway and upcoming
  • Forestview Creek Path closure update
  • Reminders: Forestview Creek path; Piner High School bus stop

Ongoing traffic control – Piner Road/Fulton Road

Traffic control measures currently in place at the Fulton Road/Piner Road intersection are expected to continue through Monday of next week. On these days the traffic signal will be turned to flashing red between the hours of 8:30 A.M. and 4:00 P.M. Please be prepared for traffic delays at the intersection, as a new 42″ storm drain pipeline is installed.

Construction underway and upcoming

NOTES: All schedules are subject to change due to unforeseen circumstances; when traveling in and near the construction areas, use additional caution and be aware of work crews, flaggers, traffic control and special signage, and heavy equipment.

  • Jenes Lane to the north access to Piner High School
    • Northbound: installation of the sidewalk is currently underway. The sidewalk in front of Piner High School is expected to be accessible to pedestrians by mid-November. Installation of the new bus stop is currently underway. Underground and surface work including installation of box culverts and pipeline is underway, and continuing into November. Please be aware of traffic impacts at the south entrance to Piner High School due to storm drain and utility work.
    • Southbound: the sidewalk in front of Youth Community Park is expected to be accessible to pedestrians by mid-November. Installation of the new bus stop is currently underway.
  • Wishing Well Way to Jenes Lane
    • Northbound: Installation of light pole foundations and concrete work including sidewalks and curbs are underway, continuing into November.
    • Southbound: underground work is continuing this week with the installation of storm drains.
  • Quail Hollow Drive to Piner Road
    • Southbound: installation of underground storm drains is currently underway and expected to continue into November.
  • Appletree Drive to Wishing Well Lane
    • Southbound: underground work and retaining wall construction are underway.

Forestview Creek Path Closure Update

As of early August, the Forestview Creek path is closed 24/7 from Fulton Road to Country Manor Drive, for the construction of a retaining wall and other concrete work near the creek.

For the protection of the creek and habitat, State environmental regulations establish the seasonal periods during which concrete work can take place in or near a creek (including the potential for rain). Crews have been working to complete those elements before the end of the allowed period, however it is now very likely that work at the creek will be suspended until that “window” opens again in late spring of 2023.

Therefore, the Forestview Creek path is likely to remain closed to public use until late spring/early summer of 2023. An update will be provided once the anticipated schedule is finalized. We apologize for any disruption or inconvenience that this extension of the path closure may cause. As an alternative, path users may want to consider using the Peterson Creek path between Guerneville Road and Fulton Road.

Reminders:

Piner High School bus stop – as of early July, the northbound bus stop at Piner High School is temporarily relocated to just north of the school’s main entrance. Work is underway on the new bus stop at the original location with an estimated reopening this fall. For general bus service information please visit Santa Rosa CityBus.

Installing the new 42" storm drain pipeline
Installing the new 42″ storm drain pipeline

 

Compacting the fill for the widening of Fulton Road
Compacting the fill for the widening of Fulton Road

 

Project overview and schedule

This project will widen, reconstruct, and rehabilitate one mile of Fulton Road between Guerneville Road and Piner Road, transforming it into an updated, four-lane regional/arterial street, as well as provide many other improvements. The project is expected to continue for approximately 18 – 24 months (all schedules are subject to change depending on weather, unanticipated circumstances, and seasonal access restrictions to creek areas).

Work hours: 7 am to 7 pm Monday through Friday. With City approval, periodic work on nights (8:30 pm to 5:00 am) or weekends may take place.

Additional project overview and overall schedule information is online at www.FultonRoadProject.com.