Construction Update October 14, 2022

posted in: Construction Updates | 0

In this issue:

  • Possible weekend work
  • Upcoming traffic control – Piner Road/Fulton Road
  • Construction underway and upcoming
  • Reminders: Forestview Creek path; Piner High School bus stop

Possible weekend work

Work may be scheduled for this Saturday and/or Sunday at various locations on Fulton Road, pending city approval. Traffic delays are likely to occur in the impacted areas when traffic control measures are in place. Motorists should consider taking alternate routes when possible.

Upcoming traffic control – Piner Road/Fulton Road

Traffic control measures are tentatively scheduled to be in place at the Fulton Road/Piner Road intersection starting late next week or the week of October 24 (schedule subject to change). Once underway, this work is anticipated to last for up to 3-4 days. During this time the traffic control signal will be turned to flashing red. As a result, please plan for the possibility of traffic delays occurring at the intersection. We will provide an update on the schedule for this work as soon as more definite information is available.

Construction underway and upcoming

NOTES: All schedules are subject to change due to unforeseen circumstances; when traveling in and near the construction areas, use additional caution and be aware of work crews, flaggers, traffic control and special signage, and heavy equipment.

  • Jenes Lane to the north access to Piner High School
    • Northbound: installation of the sidewalk is currently underway. The sidewalk in front of Piner High School is expected to be accessible to pedestrians by late October. Installation of the new bus stop is currently underway. Underground and surface work including installation of box culverts and pipeline is underway, and continuing through October. Please be aware of traffic impacts at the south entrance to Piner High School due to storm drain and utility work.
    • Southbound: the sidewalk in front of Youth Community Park is expected to be accessible to pedestrians by mid to late October. Installation of the new bus stop is currently underway.
  • Wishing Well Way to Jenes Lane
    • Northbound: Installation of light pole foundations and concrete work including sidewalks and curbs are underway, continuing through October.
    • Southbound: underground work started this week with the installation of storm drains.
  • Quail Hollow Drive to Piner Road
    • Southbound: installation of underground storm drains is currently underway and expected to continue through October.
  • Appletree Drive to Wishing Well Lane
    • Southbound: underground work and retaining wall construction are underway.

Reminders:

  • Forestview Creek path – as of early August, the Forestview Creek path is closed 24/7 from Fulton Road to Country Manor Drive, for the construction of a retaining wall, with the reopening anticipated in November. We apologize for any inconvenience to those who use this path. As an alternative, path users may want to consider using the Peterson Creek path between Guerneville Road and Fulton Road.
  • Piner High School bus stop – as of early July, the northbound bus stop at Piner High School is temporarily relocated to just north of the school’s main entrance. Work is underway on the new bus stop at the original location with an estimated reopening this fall. For general bus service information please visit Santa Rosa CityBus.
Pouring concrete for a new retaining wall
Pouring concrete for a new retaining wall

 

Sterilization of a water service pipe prior to installation
Sterilization of a water service pipe prior to installation

 

Project overview and schedule
This project will widen, reconstruct, and rehabilitate one mile of Fulton Road between Guerneville Road and Piner Road, transforming it into an updated, four-lane regional/arterial street, as well as provide many other improvements. The project is expected to continue for approximately 18 – 24 months (all schedules are subject to change depending on weather, unanticipated circumstances, and seasonal access restrictions to creek areas).

Work hours: 7 am to 7 pm Monday through Friday. With City approval, periodic work on nights (8:30 pm to 5:00 am) or weekends may take place.

Additional project overview and overall schedule information is online at www.FultonRoadProject.com.