In this issue:
- Traffic Control Update
- Project Update
- Construction Photos
- Construction Underway and Upcoming
- Project Overview
Traffic Control Update
[updated!] The 24-hour traffic controls in place along Fulton Road between Piner Road and Guerneville Road were removed this week, with all four vehicle lanes and two bike lanes now fully open. While some work remains, traffic control will be limited to specific areas where work is still in progress. We appreciate your continued patience as we complete this essential project.Project Update
The current projected end date for the pavement repair work is October 2024. Note – the end date is largely dependent on the contractor’s schedule and whether city inspectors can sign off on the work.
City staff are currently inspecting the contractor’s recent work to ensure it meets the contract specifications. Any panels that do not comply with the contract will be replaced at the contractor’s expense.
When traveling in or near the construction areas, be cautious and aware of work crews, flaggers, traffic control, rough roadways, special signage, and heavy equipment. Please be prepared for temporary traffic control measures throughout the work area.
Construction Photos
Construction Underway and Upcoming
The final work that will get underway after pavement replacement is complete includes:
- Asphalt paving of the intersection of Piner Road and Guerneville Road
- Landscaping in the medians and sidewalks
- Lane restriping
- Addressing various smaller “punch list” items
Most of these items will not significantly impact the public or the use of the roadway. We anticipate that these final work items will be finished and the completed roadway will be fully open to the public approximately one month after the pavement replacement is competed and has been deemed acceptable.
All schedules are subject to change due to weather and unforeseen circumstances. Be sure to visit www.FultonRoadProject.com for up-to-date information.
Reminders
- Installation of bus shelters and benches is complete, however not all of them are in use due to the temporary traffic controls that are currently in place. For general bus service information, please visit Santa Rosa CityBus.
Project Overview
This project will widen, reconstruct, and rehabilitate one mile of Fulton Road between Guerneville Road and Piner Road, transforming it into an updated, four-lane regional/arterial street, as well as provide many other improvements.
Work hours: 7 A.M. to 7 P.M. Monday thru Friday. With City approval, periodic work on nights (8:30 P.M. to 5:00 A.M.) or weekends may take place.
Additional project overview and overall schedule information is online at www.FultonRoadProject.com.
If you have questions or concerns about this project, send an email to info@FultonRoadProject.com or call the project information line at (707) 385-1239.
Thank you for your patience and cooperation!