Intersection Work Upcoming
[updated!] The contractor is scheduled to work at the Piner Road intersection, the Wishing Well Lane intersection, and the Appletree Lane intersection on Friday, June 28. This will involve saw cutting, demolition, and pouring new concrete. To accommodate this work traffic has been shifted into the two northbound lanes from Piner Road to just north of Guerneville Road. During this work there may be temporarily limited access to driveways at some locations – the contractor will notify those residences where limited access is likely to occur.Starting Monday, July 1, the contractor will begin diamond grinding in the all of the intersections throughout the work zone was concrete was recently poured. Once completed, city staff will conduct a review of the road surface to ensure it meets the specifications within the contract. The contractor will not be on-site working on July 4 and July 5 in observance of the Fourth of July holiday.
Please note that upcoming saw cutting in some areas may continue past normal work hours into the early evening, but not at night.
When traveling in and near the construction areas, be cautious and aware of work crews, flaggers, traffic control, rough roadways, special signage, and heavy equipment. Please be prepared for temporary traffic control measures throughout the work area.
Construction Underway and Upcoming
In the coming weeks the contractor will begin working in the various intersections on Fulton Road between Piner Road and Guerneville Road. Details on any possible night work and road detours associated with this work will be provided when the schedule is developed.
- Pavement repair work is currently underway and taking place throughout the project site
- Work on roadway medians is continuing
- Installation of irrigation main and laterals is continuing
All schedules are subject to change due to weather and unforeseen circumstances. Be sure to visit www.FultonRoadProject.com for up-to-date information.
Construction Photos
Reminders
- Installation of bus shelters and benches is complete, however not all of them are in use due to the temporary traffic controls that are currently in place. For general bus service information, please visit Santa Rosa CityBus.
Project Overview and Schedule
This project will widen, reconstruct, and rehabilitate one mile of Fulton Road between Guerneville Road and Piner Road, transforming it into an updated, four-lane regional/arterial street, as well as provide many other improvements. The project started in June 2022 and is expected to last for approximately 24 months (all schedules are subject to change depending on weather, unanticipated circumstances, and seasonal access restrictions to creek areas).
Work hours: 7 A.M. to 7 P.M. Monday thru Friday. With City approval, periodic work on nights (8:30 P.M. to 5:00 A.M.) or weekends may take place.
Additional project overview and overall schedule information is online at www.FultonRoadProject.com.
If you have questions or concerns about this project, send an email to info@FultonRoadProject.com or call the project information line at (707) 385-1239.