In this issue:
- Road Surface Repairs
- Construction Underway and Upcoming
- Reminders
- Bus shelters/benches
- Project Overview and Schedule
Road Surface Repairs
[updated!] The contractor is in the process of diamond-grinding the newly installed surface on the two northbound (east side) lanes of Fulton Road, to ensure a smooth road surface. To accommodate this work, both directions of traffic along this section of Fulton Road have been moved to the southbound (west) side.Saw cutting/demolition and concrete work on the North Access Road at Piner High School is underway, and expected to be finished this week.
Please note that upcoming saw cutting in some areas may continue past normal work hours into the early evening, but not at night.
When traveling in and near the construction areas, be cautious and aware of work crews, flaggers, traffic control, rough roadways, special signage, and heavy equipment. Please be prepared for temporary traffic control measures throughout the work area.
Construction Underway and Upcoming
In the coming weeks the contractor will begin working in the various intersections on Fulton Road between Piner Road and Guerneville Road. Details on any possible night work and road detours associated with this work will be provided when the schedule is developed.
- Pavement repair work is currently underway and taking place throughout the project site
- Work on roadway medians is continuing
- Installation of irrigation main and laterals is continuing
All schedules are subject to change due to weather and unforeseen circumstances. Be sure to visit www.FultonRoadProject.com for up-to-date information.
Reminders
- A HAWK Signalized Crosswalk has been installed between Piner High School and Youth Community Park on Fulton Road, which stops vehicle traffic only when activated by a pedestrian. This is the third HAWK beacon crossing installed within the city limits. For more information on HAWK signalized crosswalks, please visit the city website.
- The Fulton Road northbound bus stop near Quail Hollow Drive has been temporarily relocated to the eastbound lane of Piner Road, near the Fulton Road and Piner Road intersection. The Fulton Road northbound bus stop near Guerneville Road has been temporarily relocated just south of the Guerneville Road intersection. For general bus service information, please visit Santa Rosa CityBus.
Project Overview and Schedule
This project will widen, reconstruct, and rehabilitate one mile of Fulton Road between Guerneville Road and Piner Road, transforming it into an updated, four-lane regional/arterial street, as well as provide many other improvements. The project started in June 2022 and is expected to last for approximately 24 months (all schedules are subject to change depending on weather, unanticipated circumstances, and seasonal access restrictions to creek areas).
Work hours: 7 A.M. to 7 P.M. Monday thru Friday. With City approval, periodic work on nights (8:30 P.M. to 5:00 A.M.) or weekends may take place.
Additional project overview and overall schedule information is online at www.FultonRoadProject.com.
If you have questions or concerns about this project, send an email to info@FultonRoadProject.com or call the project information line at (707) 385-1239.
Thank you for your patience and cooperation!