Construction Update November 18, 2022

posted in: Construction Updates | 0

In this issue:

  • Piner High School and Youth Community Park access
  • Construction underway and upcoming
  • Forestview Creek Path closure update
  • Reminder: Piner High School bus stop

Piner High School and Youth Community Park access

Starting Monday, November 28 and continuing for an estimated three days, crews will be paving the access driveways to both Piner High School and Youth Community Park. A portion of each driveway will remain open and available for access. Traffic control measures will be in place during this time, and motorists wishing to enter or exit these locations may experience short delays.

Construction underway and upcoming

NOTES: Due to the Thanksgiving holiday, crews will not be working Thursday and Friday of next week (11/24 and 11/25).

All schedules are subject to change due to weather and unforeseen circumstances; when traveling in and near the construction areas, use additional caution and be aware of work crews, flaggers, traffic control, rough roadways, special signage, and heavy equipment.

  • Guerneville Rd to Wishing Well Lane
    • Southbound: underground work, sidewalk removal / re-configuration, and retaining wall construction are underway. Construction of the sidewalk is currently underway.
  • Wishing Well Way to Jenes Lane
    • Northbound: installation of light pole foundations is continuing through November.
    • Southbound: underground work is continuing this week with the installation of storm drains.
  • Jenes Lane to Piner High School
    • Northbound: installation of the sidewalk is currently underway. Installation of the new sidewalk in front of Piner High School is nearly complete and is expected to be accessible to pedestrians within the next few weeks. Installation of the new bus stop is currently underway. Please be aware of traffic impacts at the south entrance to Piner High School due to storm drain and utility work.
    • Southbound: construction of the sidewalk in front of Youth Community Park is underway and it’s expected to be accessible to pedestrians by the end of this week. Installation of the new bus stop is currently underway.
  • Piner High School to Piner Road
    • Southbound: installation of underground storm drains is currently underway and expected to continue through November. Construction of the new sidewalk is expected to begin soon.

Forestview Creek Path Closure Update

As of early August, the Forestview Creek path is closed 24/7 from Fulton Road to Country Manor Drive, for the construction of a retaining wall and other concrete work near the creek.

For the protection of the creek and habitat, State environmental regulations establish the seasonal periods during which concrete work can take place in or near a creek (including the potential for rain). Crews have been working to complete those elements before the end of the allowed period, however it is now very likely that work at the creek will be suspended until that “window” opens again in late spring of 2023.

Therefore, the Forestview Creek path is likely to remain closed to public use until late spring/early summer of 2023.

An update will be provided once the anticipated schedule is finalized. We apologize for any disruption or inconvenience that this extension of the path closure may cause. As an alternative, path users may want to consider using the Peterson Creek path between Guerneville Road and Fulton Road.

Reminder:

Piner High School bus stop – as of early July, the northbound bus stop at Piner High School is temporarily relocated to just north of the school’s main entrance. Work is underway on the new bus stop at the original location with an estimated reopening later this fall. For general bus service information please visit Santa Rosa CityBus.

Pulling new fiber optic cable under the sidewalk for traffic signals
Pulling new fiber optic cable under the sidewalk for traffic signals

 

Installing a new storm drain drop inlet
Installing a new storm drain drop inlet

Project overview and schedule

This project will widen, reconstruct, and rehabilitate one mile of Fulton Road between Guerneville Road and Piner Road, transforming it into an updated, four-lane regional/arterial street, as well as provide many other improvements. The project is expected to continue for approximately 18 – 24 months (all schedules are subject to change depending on weather, unanticipated circumstances, and seasonal access restrictions to creek areas).

Work hours: 7 am to 7 pm Monday through Friday. With City approval, periodic work on nights (8:30 pm to 5:00 am) or weekends may take place.

Additional project overview and overall schedule information is online at www.FultonRoadProject.com.